October 22, 2012, at 4:02 PM

Original link

1.   That it BE NOTED that no pecuniary

interests were disclosed.

2.   2nd Report of the

Transportation Advisory Committee

Recommendation:  That the 2nd Report of the Transportation Advisory Committee, from its meeting held on October 2, 2012, BE RECEIVED.

3.   The Standard of

Care Provision in Ontario’s Safe Drinking Water Act, 2002

Recommendation:  That the following actions be taken with respect to the Standard of Care Provision in Ontario’s Safe Drinking Water Act, 2002:   a)         the report dated October 22, 2012 from the Managing Director, Engineering and City Engineer, with respect to Section 19 of the Ontario’s Safe Drinking Water Act, 2002, commonly referred to as the “Standard of Care Provision”, BE RECEIVED for information; and,   b)         the City Solicitor BE REQUESTED to provide a report back at a future meeting of the Civic Works Committee with respect to legal protection for Councillors in regard to the associated legal liabilities and penalties, as well as any other implications or repercussions of the legislation outlined in Section 19 of the Ontario’s Safe Drinking Water Act, 2002, that extends legal responsibility to people with decision-making authority over municipal drinking water systems.  (2012-W13-00)

4.   Amendments to the

Traffic and Parking By-law

Recommendation:  That, on the recommendation of the Managing Director, Engineering and City Engineer, the attached proposed by-law (Appendix “A”) BE INTRODUCED at the Municipal Council meeting to be held on October 30, 2012, for the purpose of amending the Traffic and Parking By-law (P.S. 111).  (2012-G05-00)

5.   Appointment of

Consulting Services for the Dingman Creek Subwatershed Study - Climate Change Update

Recommendation:  That, on the recommendation of the Managing Director, Engineering and City Engineer, the following actions be taken with respect to the appointment of a consultant for the Dingman Creek Subwatershed Study, climate change update:   a)         Delcan (Consultant), 1069 Wellington Road South, Suite 214, London, ON, N6E 2H6, BE APPOINTED as Consulting Engineers for the Dingman Creek Subwatershed Study Update in the amount of $327,159, excluding H.S.T., including allowances for contingency and provisional items for a physical survey and a Westminster Wetland Investigation and Water Balance Review, in accordance with Section 15, Clause 15.2(d) of the Procurement of Goods and Services Policy;   b)         the financing for this project BE APPROVED as set out in the Sources of Financing Report included as Appendix “A” to the associated staff report, dated October 22, 2012;   c)         the consulting fees for the project identified in (a), above, BE IN ACCORDANCE with the estimate, on file, which is based upon the Fee Guideline for Professional Engineering Services, 2006, recommended by the Ontario Society of Professional Engineers;   d)         the approvals hereby BE CONDITIONAL upon the Corporation entering into a formal contract with the consultant for the work; and,   e)         the Mayor and the City Clerk BE AUTHORIZED to execute any contract or other documents, if required, to give effect to these recommendations.  (2012-A03-00)

6.   Appointment of

Consulting Services for Medway Creek Subwatershed Study Update

Recommendation:  That, on the recommendation of the Managing Director, Engineering and City Engineer, the following actions be taken with respect to the appointment of a consultant for the Medway Creek Subwatershed Study Update:   a)         Dillon Consulting, 1400-130 Dufferin Avenue, London ON, N6A 5R2, BE APPOINTED as Consulting Engineers for the Medway Creek Subwatershed Study Update, in the amount of $293,814, including a contingency allowance of $50,000, excluding H.S.T., in accordance with Section 15, Clause 15.2(d) of the Procurement of Goods and Services Policy;   b)         the financing for this project BE APPROVED as set out in the Sources of Financing Report included as Appendix “A” to the associated staff report, dated October 22, 2012;   c)         the consulting fees for the project identified in (a), above, BE IN ACCORDANCE with the estimate, on file, which are based upon the Fee Guideline for Professional Engineering Services, 2006, recommended by the Ontario Society of Professional Engineers;   d)         the approvals hereby BE CONDITIONAL upon the Corporation entering into a formal contract with the consultant for the work; and,   e)         the Mayor and the City Clerk BE AUTHORIZED to execute any contract or other documents, if required, to give effect to these recommendations. (2012-A03-00)

7.   New “Value

Based” Funding Model for Water and Wastewater Services

Recommendation:  That the following actions be taken with respect to the new “Value Based” funding model for Water and Wastewater Services:   a)         the report dated October 22, 2012, from the Managing Director of Engineering and City Engineer BE RECEIVED for information;   b)         a Public Participation Meeting BE HELD at the November 12, 2012 meeting of the Civic Works Committee, to hear from the public with respect to the proposed new “Value Based” funding model for Water and Wastewater Services; and,   c)         the Civic Administration BE REQUESTED to include Schedules B1 through B5 of Appendix B – “Schedule for Various Customer Benefits”, associated to the staff report dated October 22, 2012, for consideration at the above-noted Public Participation Meeting; it being noted that the Civic Works Committee heard the attached presentation and received the attached additional presentation, entitled “Total Annual Charges”, from the Managing Director of Engineering and City Engineer, and R. Welker, Division Manager, Water Engineering, with respect to this matter.  (2012-F17-00)

8.   Repaving of

Berkshire Court

Recommendation:  That the communication dated September 21, 2012, from R.J. Tolmie, Secretary, London Condominium Corporation No. 11 and K. W. Sadler, President and Director, London Condominium Corporation No. 4, BE RECEIVED; it being noted that the Civic Administration communicated with Mr. Tolmie and Mr. Sadler on September 28, 2012, indicating that Berkshire Court has been included in the 2013 work program proposed in the 2013 Capital Works Budget.  (2012-S08-00)

9.   Parallel Parking at

End of Driveway

Recommendation:  That the Director, Roads and Transportation BE REQUESTED to review and report back at a future meeting of the Civic Works Committee (CWC) with respect to the communication dated October 4, 2012, from David Burdan, 68 Hillhead Road, related to parallel parking at the end of driveways; it being noted that Mr. Burdan is to be given delegation status when the report comes back to the CWC.

10.   Water Usage Charges

Recommendation:  That the Managing Director, Engineering and City Engineer BE REQUESTED to review and report back at a future meeting of the Civic Works Committee (CWC) with respect to the communication dated September 28, 2012, from Lynne Stein, 20-475 McGarrell Drive, relating to a request for a refund on water usage charges; it being noted that Ms. Stein is to be given delegation status when the report comes back to the CWC; it being further noted that the CWC heard a verbal update from Councillor M. Brown, with respect to this matter.  (2012-W13-00)

11.   Economic

Development Opportunities for London

Recommendation:  That the following actions be taken with respect to the communication dated October 5, 2012, from H. Brown, President, Brown and Cohen Communications and Public Affairs Inc., requesting delegation status for G. Mulhern, Executive Director, Ontario Concrete Pipe Association and B. Brown, President, Coldstream Concrete, with respect to economic development opportunities for London:   a)         the communication BE REFERRED to the Investment and Economic Prosperity Committee (IEPC); and,   b)         the Managing Director, Engineering and City Engineer BE REQUESTED to provide a report advising on the policies for the procurement of services or products followed by the Engineering service area.